Arbeidsgiver
Salzburg AG, Pinzgau
Designer/planlegger/formgiver
Salzburg AG, Pinzgau
Fullføringstid/gjennomføringstid
2012 - 2014
Gjennomføring av arbeid
ARGE KW Bärenwerk
Firmapartner
Marti GmbH, AT-8010 Graz
Marti GmbH Deutschland, DE-70567 Stuttgart
Marti Tunnelbau AG, CH-3302 Moosseedorf
Hovedentreprenør- Teknisk og kommersiell lederskap
Marti GmbH, AT-8010 Graz
Mer…
Mindre…
Arbeidets omfang
Upgrade of the power plant Bärenwerk in Fusch, on the Grossglockner. The main measures are the construction of the underground waterway gallery and the new dam.
- Waterway Ø 3.8 m
- Tilt 4.8 %
- Length 3'275 m
Technical Specifications
- Operator: Salzburg AG
- Plant type: Hydropower plant
- Commissioning: 1924
- Yield (+28 %): 14'960 kW instead of 11'600 kW
- Annual production (+17 %): 66.3 Mio. kWh instead of 56.9 Mio. kWh
- Turbines: 3 Pelton turbines
- Tank: daily storage in Ferleiten
- Height of fall: 290 m
- Flow: 6.45 m³/s instead of 5.35 m³/s
Aktiviteter
100 m with counter-jacking D&B
15 % slope
280 m gallery D&B
2'835 m penstock TBM Ø 3.8 m
2'935 m inner shell of 600 m with sealing