Client
Deutsche Bahn AG, DE-99001 Erfurt
Engineer
DB ProjektBau GmbH, DE-04003 Leipzig
Time of Completion
2010 - 2013
Contract Sum
CHF 100 Mio.
Execution of the Work
ARGE Tunnel Feuerfelsen Rennberg
Consortium Partners
Marti Tunnelbau AG, CH-3302 Moosseedorf
Marti GmbH, DE-70567 Stuttgart
Johann Bunte Bauunternehmung GmbH & Co.KG,
DE-26871 Papenburg
Lead Company and Technical Lead
Marti Tunnelbau AG, CH-3302 Moosseedorf
Commercial Lead
Johann Bunte Bauunternehmung GmbH & Co.KG,
DE-26871 Papenburg
More…
Less…
Scope of the Works
Two-track railway tunnel. VDE 8.1 new railway section Ebensfeld – Erfurt, BA 3121, VP Coburg Ost, NBS Bau-km 19,1+30 – 24,8+95
Activities
The road project Coburg East is part of the road traffic master plan Deutsche Einheit Nr. 8.1, new highway Nürnberg-Erfurt-Leipzig/Halle-Berlin.
The contract embraces a 5.8 km long stretch including the tunnel Feuerfelsen 1’003 m, the tunnel Rennberg 1’032 m, five bridges, the roadwork and earthwork of 2.2 mill. cubic meter.
Execution and schedule :
The tunnels are realized with a two shell in-lining, being the outer shell of shotcrete and the inner one of concrete. The tunnel section has 160 m2 and both tunnels are excavated simultaneously. The excavation is realized applying the conventional NATM. Works started in August 2010 with the excavation of the trench of the Southern portal of the tunnel Feuerfelsen. The tunnelling work started in January 2011. For the completion of both tunnels a schedule of 21 months was set.
Length: 1 x 1’003 m
1 x 1’032 m
Excavation volume: 320’000 m³
Shotcrete/concrete volume: ca. 170’000 m³
Arming steel inner shell: ca. 8'000 t
Construction method: NATM
(D&B with heading, bench and bottom)
Pull length: max. 2,2 m
Diameter of the tube: 12 m
Minimal covering: 10 m
Maximal covering: 25 m
Escape gallery L = 150 m and escape shaft
Planned speed-limit: 300 km/h
Geology
Both tunnels Feuerfelsen and Rennberg are driven on their whole length through formations of coloured sandstone. The tunnels have a covering of 10 to 25 meters. Due to ground water the construction is shielded with a KDB insulation.